How does Primavera calculate earned value?
Earned Value Cost is the value of the work performed as of the data date and is calculated as: Earned Value Cost = Budget at Completion x Performance % Complete. In Primavera P6, the method for calculating the Performance Percent Complete technique is selected at the WBS level.
How does Primavera calculate performance complete?
The Performance % Complete specifies what percentage of the activity’s planned worth has been earned so far. Note: Summary Performance percent complete when displayed on an organize band, will ALWAYS be calculated as (BCWP * 100) / BAC, regardless of what earned value technique is selected for the activity’s WBS.
How does p6 calculate SPI?
Schedule Performance Index (SPI) measures the physical work accomplished against the amount of work that was planned and is calculated as SPI = Earned Value Cost/Planned Value Cost.
What is EVM in Primavera?

by Lauren Hecker | Dec 29, 2021 | Primavera P6 | 0 comments. Earned Value Management (EVM), otherwise known as earned value analysis, is a technique to measure the performance and progress of a project. The basic premise of earned value is that the cost spent is relative to the work completed.
What is Earned Value formula?
Earned Value (EV) = total project budget multiplied by the % of project completion.
What earned value?
Earned value (EV) is a way to measure and monitor the level of work completed on a project against the plan. Simply put, it’s a quick way to tell if you’re behind schedule or over budget on your project. You can calculate the EV of a project by multiplying the percentage complete by the total project budget.
How does Primavera calculate planned progress?
Schedule % Complete = PV / BAC This is the planned value divided by budget at completion. Again, this is the planned schedule cost in relation to the DD and not the current schedule cost.
What is earned value in Primavera p6?
Earned Value (EV) is a monetary value for the progress of work completed. Put simply, this is the amount of money that should have been spent for the amount of work that has been completed. Actual Cost (AC) is the actual monetary value spent on the project.
How do I create a monthly cost report in Primavera P6?
Primavera P6 Professional has a time phased reporting feature to provide the monthly budgeted total cost of the project. Let’s proceed and create a time phased budgeted cost report. To generate a report select the reports icon in the enterprise menu and select Edit | + Add. This activates the report wizard.
How do you generate cash flow in Primavera P6?
1- Open reports section from tools tap then reports then reports as per photo below :
- Open report tap in primavera p6.
- Select monthly cash flow report.
- click next on primavera report.
- click column icon to adjust primavera report.
- select planned value and earned value.
- Click next in report wizard.
What is the purpose of earned value management?
EVM helps provide the basis to assess work progress against a baseline plan, relates technical, time and cost performance, provides data for pro-active management action and provides managers with a summary of effective decision making.
How can I learn EVM?
Understanding Earned Value Management
- The first step is to define the work.
- The second step is to assign a value, called planned value (PV), to each activity.
- The third step is to define “earning rules” for each activity.
- The final step is to execute the project according to the plan and measure progress.
What are the three earned value analysis Formulae?
EAC3 = AC + ((BAC – EV) / (CPI x SPI)) or BAC/(CPI x SPI). This formula considers both cost and schedule impact on the EAC, and usually yields the most pessimistic EAC for a project not doing well.
How do you analyze earned value?
The 8 Steps to Earned Value Analysis
- Determine the percent complete of each task.
- Determine Planned Value (PV).
- Determine Earned Value (EV).
- Obtain Actual Cost (AC).
- Calculate Schedule Variance (SV).
- Calculate Cost Variance (CV).
- Calculate Other Status Indicators (SPI, CPI, EAC, ETC, and TCPI)
- Compile Results.
How do you find performance percentage?
Percentage Change | Increase and Decrease
- First: work out the difference (increase) between the two numbers you are comparing.
- Increase = New Number – Original Number.
- Then: divide the increase by the original number and multiply the answer by 100.
- % increase = Increase ÷ Original Number × 100.
What if SPI is less than 1?
If the SPI is 1, then the project is progressing exactly as planned. If the SPI is less than 1 then the project is running behind schedule.